Non-Compliance detail


  
Summary
 
Licence number: 601
Annual Return Start: 01 Jun 2008
Annual Return End: 31 May 2009
Date Received: 28 Jul 2009
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M2.1 Monitoring Point 8 (DDG-C8) was not sampled for Nov 08, due to the Dust Gauge being damaged and a valid sample was unable to be taken. Appropriate Action taken by licensee 1
M2.1 The monitoring of Total Suspended Particulates at Monitoring Point 9 (HVAS-C1) must be conducted every 6 days. There was 1 occasion where a sample was not taken on the sixth day, due to a power failure. (16/6/08) Appropriate Action taken by licensee 1